January Production Reports – 2018
All projects with the exception of Harpster, WP Marion, and WP Ottawa exceeded their P50 productions estimates. SCADA data was available for WP Marion for the entire month of January so all project performance metrics have been included in the report. WP Ottawa has been added to the fleet report with production numbers being taken from the meter, full project performance information will be included in February.
All outstanding planned maintenance events were completed in January and the report includes the anticipated dates for the next round of maintenance events. The 500 hour maintenance at Whirlpool Ottawa is scheduled to be completed in February