Performance just over expected (P50) forecast. Yaw brake replacement completed at W1; W2 will be addressed in February. Annual maintenance planned for late February.
Performance just under expected (P50) forecast. Standoff bracket issue (NCR 019-2-001) issue was solved at Z2. Yaw brake replacement completed at Z1 & Z2; Z3 will be addressed in February. Annual maintenance planned for late February.
Performance ~20% under expected (P50) forecast. Yaw brake replacement completed. Annual maintenance planned for early March. Stay tuned for adjusted annual P50 monthly distribution (coming in February).
Good performance; higher than expected production. Blade repair on Turbine C completed (NCR 016-2-002).
Performance just over expected (P50) forecast despite downtime (>2 wks) at Turbine 3. Temporary blade repair was completed at Turbine 3; minor pinhole repaired at Turbine 2.